Department of Park & Side Walks
S.N |
Project Name |
Value (SAR) |
Duration |
Start Date |
Completed On |
Completion |
1 |
Maintenance of Prince Muhammad bin Nasser Park in Jazan |
2474000 |
200 days |
19/1/1435 |
15/7/1435 |
100% |
2 |
Establishing and equipping public parks in Jazan City, the second phase) |
6497813 |
350 days |
5/07/1434 |
20/06/1435 |
100% |
3 |
Maintenance of sidewalks at the eastern entrance to the center in Al-Saha |
2997500 |
180 days |
13/11/1435 |
13/03/1436 |
100% |
4 |
Street maintenance in the city of Jazan. The process of maintaining street sidewalks according to plan 6D (C) in the city of Jazan |
4144531 |
120 days |
6/01/1437 |
26/08/1437 |
100% |
5 |
Improving and beautifying the entrances to the municipality and the municipalities and villages associated with it in Jazan. |
3371974 |
350 days |
19/8/1432 |
23/07/1433 |
100% |
6 |
Maintenance and improvement of sidewalks at Al-Shuqairi Center in Damad |
3730750 |
350 days |
22/9/1439 |
14/09/1440 |
100% |
7 |
Maintenance of street sidewalks in Jazan City |
8464087 |
1096 days |
24/03/1440 |
4/4/1443 |
100% |
8 |
Maintenance of tiles on Cultural Street in Samtah |
2429843 |
1188 days |
09/04/1443 |
12/8/1443 |
100% |
9 |
Maintenance of gardens, green spaces, pedestrian walkways, squares, and irrigation networks in Jazan (maintenance of the Northern Corniche Road - the first phase) |
1989076.98 |
270 days |
10/06/1443 |
24/1/1444 |
100% |
10 |
Treating visual distortion in Saudi cities. Repairing potholes in streets and sidewalks in Jazan City |
6259050 |
180 days |
30/4/1440 |
14/10/1440 |
100% |
Total Contract Value for of Parks and Sidewalks: 42,624.98358 SAR Only forty-two million three hundred
fifty-eight thousand Six hundred twenty-four riyals and ninety-eight halalas.
Contstruction Departments
S.N |
Project Name |
Value (SAR) |
Duration |
Start Date |
Completed On |
Completion |
1 |
Expansion of staff housing at Yanbu Technical Institute - Yanbu Industrial City.Royal Commission for Jubail and Yanbu |
32667618 |
200 days |
9/13/17 |
09/11/1441 |
100% |
2 |
Developing the maternity department at Samta Hospital. |
20477882 |
11 Months |
09/07/1443 |
09/07/1441 |
100% |
3 |
Establishing a dining hall in the Diwan of the Emirate |
925942.5 |
9 Months |
|
|
100% |
4 |
Al-Husseini School in Sabya, Jazan |
8283439 |
|
|
|
100% |
5 |
King Faisal School in Sabya, Jazan |
9118350 |
|
|
|
100% |
6 |
Establishment of the municipality building |
6930000 |
|
|
|
100% |
7 |
Rainwater drainage in Dehma and King Abdullah Housing in Al-Sahi |
10996687 |
500 days |
24/03/1440 |
|
98.17% |
8 |
Establishment of a health clinic, Sector 1,District No. 2 |
17000000 |
1080 days |
20/07/1441 |
|
85% |
9 |
Completion of the secretariat building in Jazan M2 |
13901096 |
240 days |
23/04/1443 |
|
62.83% |
10 |
Maintenance of rainwater drainage culverts in Jazan (maintenance of the waterrepellent line in the central region and critical points |
4182032.5 |
150 days |
18/10/1443 |
|
81.07% |
Total construction value: 124,481,947.43 SAR
Only one hundred twenty-four million four
hundred and eighty-one thousand Nine hundred and forty-seven riyals and forty-three halalas
Mechnical Section
S.N |
Project Name |
Owner |
Value (SAR) |
Duration |
Completion |
1 |
Drainage of rainwater in Dehima and King Abdullah Housing Sehi Jazan
|
Jazan Region Municipality |
10,995,587 |
1184 days |
100% |
2 |
Maintenance of rainwater drainage culverts in Jizan (Maintenance of Water repellent in the central area and critical points)
|
Jazan Region Municipality |
4,182,032.50 |
286 Days |
100% |
3 |
Construction of a sewage lifting station for the Boat Pavilion Marine port in Jazan.
|
Jazan Region Municipality |
10,995,587 |
1184 Days |
100% |
4 |
Maintenance of rainwater drainage in Jizan.
|
Jazan Region Municipality |
7,896,440 |
36 Months |
100% |
5 |
Drainage of rainwater and ward off the dangers of floods. Protection The villages Located on the Leyah Valley (Denduf - Mutaqa) with the lock
|
Jazan Region Municipality |
13,956,778.50 |
480 days |
100% |
6 |
Preventing the dangers of floods to the valley Ashaar, the village of Al-Hijfar And Abbah in Al-Sahi
|
Jazan Region Municipality |
15,642,704.60 |
300 days |
100% |
7 |
Drainage of rainwater in Jizan
|
Jazan Region Municipality |
10,828,595 |
360 days |
100% |
8 |
Developing and modernizing air conditioning for some departments of a hospital To Prince Muhammad bin Nasser
|
General Directorate of Health Affairs in Jazan Region |
4,584,153 |
60 days |
100% |
9 |
Rehabilitation and development of the central air conditioning system and his attachments to a hospital Prince Muhammad bin Nasser
|
General Directorate of Health Affairs from Jazan |
39,307,751.30 |
18 months |
100% |
Total Mechanical Section:
118,389,628.90 SAR
One hundred eighteen million, three hundred eighty-nine thousand, six hundred twenty-eight Saudi Riyals and ninety halalas.
Lighting Work
S.N |
Project Name |
Value (SAR) |
Duration |
Start Date |
Completed On |
Completion |
1 |
Road, sidewalks and lighting for the municipalities and municipalities (lighting)
|
2269870 |
180 days |
23/11/1435 |
9/6/1436 |
100% |
2 |
Lighting maintenance in Jazan city parks and gardens.
|
6309050 |
1095 Days |
10/04/1443 |
09/07/1441 |
100% |
3 |
Lighting maintenance. Jazan |
9497855 |
1204 Days |
24/03/1440 |
17/08/1443 |
100% |
Total Lighting Work: 18,076,775.00 SAR
Only Eighteen million, seventy-six thousand, seven hundred seventy-five Saudi Riyals