Department of Park & Side Walks

S.N Project Name Value (SAR) Duration Start Date Completed On Completion
1 Maintenance of Prince Muhammad bin Nasser Park in Jazan 2474000 200 days 19/1/1435 15/7/1435 100%
2 Establishing and equipping public parks in Jazan City, the second phase) 6497813 350 days 5/07/1434 20/06/1435 100%
3 Maintenance of sidewalks at the eastern entrance to the center in Al-Saha 2997500 180 days 13/11/1435 13/03/1436 100%
4 Street maintenance in the city of Jazan. The process of maintaining street sidewalks according to plan 6D (C) in the city of Jazan 4144531 120 days 6/01/1437 26/08/1437 100%
5 Improving and beautifying the entrances to the municipality and the municipalities and villages associated with it in Jazan. 3371974 350 days 19/8/1432 23/07/1433 100%
6 Maintenance and improvement of sidewalks at Al-Shuqairi Center in Damad 3730750 350 days 22/9/1439 14/09/1440 100%
7 Maintenance of street sidewalks in Jazan City 8464087 1096 days 24/03/1440 4/4/1443 100%
8 Maintenance of tiles on Cultural Street in Samtah 2429843 1188 days 09/04/1443 12/8/1443 100%
9 Maintenance of gardens, green spaces, pedestrian walkways, squares, and irrigation networks in Jazan (maintenance of the Northern Corniche Road - the first phase) 1989076.98 270 days 10/06/1443 24/1/1444 100%
10 Treating visual distortion in Saudi cities. Repairing potholes in streets and sidewalks in Jazan City 6259050 180 days 30/4/1440 14/10/1440 100%

Total Contract Value for of Parks and Sidewalks: 42,624.98358 SAR Only forty-two million three hundred fifty-eight thousand Six hundred twenty-four riyals and ninety-eight halalas.

Contstruction Departments

S.N Project Name Value (SAR) Duration Start Date Completed On Completion
1 Expansion of staff housing at Yanbu Technical Institute - Yanbu Industrial City.Royal Commission for Jubail and Yanbu 32667618 200 days 9/13/17 09/11/1441 100%
2 Developing the maternity department at Samta Hospital. 20477882 11 Months 09/07/1443 09/07/1441 100%
3 Establishing a dining hall in the Diwan of the Emirate 925942.5 9 Months 100%
4 Al-Husseini School in Sabya, Jazan 8283439 100%
5 King Faisal School in Sabya, Jazan 9118350 100%
6 Establishment of the municipality building 6930000 100%
7 Rainwater drainage in Dehma and King Abdullah Housing in Al-Sahi 10996687 500 days 24/03/1440 98.17%
8 Establishment of a health clinic, Sector 1,District No. 2 17000000 1080 days 20/07/1441 85%
9 Completion of the secretariat building in Jazan M2 13901096 240 days 23/04/1443 62.83%
10 Maintenance of rainwater drainage culverts in Jazan (maintenance of the waterrepellent line in the central region and critical points 4182032.5 150 days 18/10/1443 81.07%
Total construction value: 124,481,947.43 SAR Only one hundred twenty-four million four hundred and eighty-one thousand Nine hundred and forty-seven riyals and forty-three halalas

Mechnical Section

S.N Project Name Owner Value (SAR) Duration Completion
1 Drainage of rainwater in Dehima and King Abdullah Housing Sehi Jazan Jazan Region Municipality 10,995,587 1184 days 100%
2 Maintenance of rainwater drainage culverts in Jizan (Maintenance of Water repellent in the central area and critical points) Jazan Region Municipality 4,182,032.50 286 Days 100%
3 Construction of a sewage lifting station for the Boat Pavilion Marine port in Jazan. Jazan Region Municipality 10,995,587 1184 Days 100%
4 Maintenance of rainwater drainage in Jizan. Jazan Region Municipality 7,896,440 36 Months 100%
5 Drainage of rainwater and ward off the dangers of floods. Protection The villages Located on the Leyah Valley (Denduf - Mutaqa) with the lock Jazan Region Municipality 13,956,778.50 480 days 100%
6 Preventing the dangers of floods to the valley Ashaar, the village of Al-Hijfar And Abbah in Al-Sahi Jazan Region Municipality 15,642,704.60 300 days 100%
7 Drainage of rainwater in Jizan Jazan Region Municipality 10,828,595 360 days 100%
8 Developing and modernizing air conditioning for some departments of a hospital To Prince Muhammad bin Nasser General Directorate of Health Affairs in Jazan Region 4,584,153 60 days 100%
9 Rehabilitation and development of the central air conditioning system and his attachments to a hospital Prince Muhammad bin Nasser General Directorate of Health Affairs from Jazan 39,307,751.30 18 months 100%

Total Mechanical Section: 118,389,628.90 SAR One hundred eighteen million, three hundred eighty-nine thousand, six hundred twenty-eight Saudi Riyals and ninety halalas.

Lighting Work

S.N Project Name Value (SAR) Duration Start Date Completed On Completion
1 Road, sidewalks and lighting for the municipalities and municipalities (lighting) 2269870 180 days 23/11/1435 9/6/1436 100%
2 Lighting maintenance in Jazan city parks and gardens. 6309050 1095 Days 10/04/1443 09/07/1441 100%
3 Lighting maintenance. Jazan 9497855 1204 Days 24/03/1440 17/08/1443 100%
Total Lighting Work: 18,076,775.00 SAR Only Eighteen million, seventy-six thousand, seven hundred seventy-five Saudi Riyals